  1. Prepare rough business analysis/reqs doc (Derek Pollard: IN PROGRESS)Complete) Pierre Dane, please review before requesting CHAI team to review. 
  2. Get CHAI review
  3. Get Akros Review
  4. Get Ona feedback
  5. One iteration
  6. Ona sign off
  7. Ona tech spec scoping
  8. Ona LOE 
  9. Ona scheduling

...

  • Peer-to-peer sync in the process by which, two or more tablets sync data across themselves without syncing to the server first. This would be done through some local network mechanism (bluetooth, hotpsot) from the devices. The outcome will be to provide offline coverage indicators.

Requirements

Sync data within a specific operational area between tablets that collected data in that operational area.

Get confirmation of what data was synced between tablets to ensure all data was sent and received.

Display coverage indicators for that operational area that reflect all synced data and filters out any duplicates to show one spray status per structure. See workflow below for indicators suggested and reason.

Views

See workflow in this google doc as I can't load the document directly.




Examples of how this previously worked in mSpray 


Image AddedImage Added

Notes

Overview of sync and offline indicators from mSpray:

...

    • Spray coverage
    • Room coverage
    • Number of structures required to get to 95%
    • Number of rooms required to get to 95%
    • * Accuracy of the calculation is key
      • Show how many records have been sent.
      • Deal with multiple data collected from the same structure
      • Is all data synced

Requirements

Sync data within a specific operational area between tablets that collected data in that operational area.

Get confirmation of what data was synced between tablets to ensure all data was sent and received.

Display coverage indicators for that operational area that reflect all synced data and filters out any duplicates to show one spray status per structure. See workflow below for indicators suggested and reason.

Views

See workflow in this google doc as I can't load the document directly.

Examples of how this previously worked in mSpray 

...

Justification


Dependencies

...