use this for initial feedback, observations and bugs - to be moved to Jira after discussion with Craig
Feedback
Overall
- Maps not loading reliably - many loading indefinitely
- Authentication page not styled
- Sessions not sticky (reloading page requires a new login)
IRS
- Create Plan
- Looks fine, but unclear why there is an option to create plan under the IRS menu and under the FI menu (which have different fields)
- View Plan
FI
- Case Triggered Plans
- No plans with draft status so unable to test what editing a case-triggered plan looks like
- Create new plan (Routine)
- Errors in selecting "Focus Area" - no options available. This was working at first but now is not
- "Focus Investigation Status" should read "Focus Status"
- Plan Title - we should add helptext to this so that there is some (at least recommended) consistency - this needs to be scoped/discussed
- We need to clarify/confirm what the start and end date of the plan mean for tasks
- Activities
- Activity "checkbox" missing
- There seems to be no way when you start a new plan to say which activities you want to do, instead you see all possible activities and the option to edit parts of them. There is no way to indicate that an activity should not be done altogether
- 'Action Field' - does this flow down to the application and show as a the label on task in the ? Or to the dashboards?
- Activity "checkbox" missing
- Team functionality not included
- Draft Routine plans not saving/displaying in the list
- Adding a new FI plan allows you to change to an IRS plan, which then gives you access to the activities section